ABC September 2026 timesheet review

Direct review of the live app on 2 October 2026. All 1,208 entry rows were available in the table; 320 were dated in September. No source records changed.

Scope: The Time Tracking view exposes date, worker, project, description, hours and Normal/Extra. It does not expose a workshop/onboard location field. This review therefore covers every September app entry and separates ABC internal work from boat/customer allocations. It cannot establish a physical workshop-only total from these fields.

ClassificationEntriesHoursShare
ABC admin/internal work67261.620.6%
Boat/customer project work2531009.579.4%
All September3201271.1100%

ABC work follows the owner’s instruction: test, phase, Taller, nave and TIME RECORDS are ABC admin/internal work. PRUEBA is included as Spanish for test. All recorded hours remain included. TIME RECORDS is also ABC work under the owner’s clarification. Different internal project names account for the earlier classification variance. These are recorded hours, not verified attendance or invoiced hours.

Findings and practical implications

  1. Capture coverage falls after the first two weeks. September 1–6: 394h; 7–13: 425.6h; 14–20: 240.7h; 21–27: 159.8h; 28–30: 51h. The last period has three calendar days. September 25 has no entries. Missing records do not establish absence or lack of work.
  2. 169 entries / 649h have placeholder descriptions. This is 51.1% of recorded hours. Hours and allocations exist, but the operation and piece cannot be reconstructed from these descriptions. The definition counts TBC, No description and No comment variants only; other vague wording also exists.
  3. Four identical pairs require confirmation. The extra copy in each pair totals 13.5h. They are candidates for duplication, not proven errors. All remain in the totals.
  4. 18 worker-days exceed eight recorded hours. Several early-month days have 14–16h marked Normal across different projects. This may be valid long days, overlap, wrong dates or duplicate capture. No start/end fields are present to determine which.
  5. Internal naming reconciled by the owner. TIME RECORDS, test, phase, Taller and nave represent ABC admin/internal projects. Combined ABC work is 261.6h across 67 entries. The names are not separate boats, and no allocation gap is claimed from these labels. Description detail still varies.
  6. Project identity is fragmented. Kimmuro 2 and Kimmora 2 are separate records (22h and 24.5h). Bm comp is split across three dated records (84.5h together). RigPro has two records (46.5h together). Mysorah and MYSORAH BARNIZ total 447h, but are retained separately. These combined views do not prove records should be merged.
  7. Entry wording conflicts with labour classification in a small subset. Four ABC entries totalling 0.5h expressly say synthetic; Linda has a further 0.1h marked dummy test. Their hours remain in ABC totals under the owner’s rule; the wording needs resolving before treating them as worked labour.
  8. Piece linkage is not shown in this view. Some Mysorah descriptions mention bow, stern or rail but explicitly leave exact piece identity unresolved. Do not assume P-001/P-002/P-003 from that wording.

Worker totals

Days means distinct dates with at least one app entry. Average is hours per recorded day, not per scheduled working day.

WorkerEntriesRecorded daysABC hoursBoat/customer hoursTotal hoursAverage/day
Abc112022.0
Adrian Barros Munoz1710078787.8
Adrian Scott321016.524.541.04.1
Arnie Galloway1811084.584.57.68
Carlos (Autonomo)220994.5
David Pedrosa Hurtado421768.564.5133.07.82
David Tejada69727168127.5135.58.47
Donald MacIntyre217188.0
Francisco Moreno Marin27152145.5147.59.83
Frederico Agusti Berger18142388.0111.07.93
J.C. Molina Gonzalez2714391.594.56.75
Joaquin Garcia Munoz161115.566.582.07.45
Jose Crespi Munoz189751.058.06.44
Lee Allinson87048.548.56.93
Linda Perusko Roberts110.100.10.1
Miguel Angel Morales Vera251550.541.091.56.1
Pedro Lopez Lombardo16841.022.563.57.94
Ruben Sola Fernandez75040408.0
Valentin Garcia Molina105526316.2
Wally210.200.20.2
Wally Abiodun4212.3012.36.15

Every day in September

DayEntriesABC hoursBoat/customer hoursTotal
1236.084.590.5
2219.080.589.5
32719.080.099.0
42223.076.099.0
55016.016.0
60000
72420.573.594.0
81719.171.590.6
91830.05484.0
10151644.060.0
111816.561.578.0
12401919
130000
142114.764.078.7
15146.050.056.0
161714.550.565.0
1782.521.023.5
188314.517.5
190000
200000
2115048.548.5
22141543.058.0
238122436
2448.3917.3
250000
260000
270000
28515621
29619.010.0
30610.59.520.0

Every project allocation

CategoryProjectEntriesHours
ABC workPRUEBA PEDRO STP - 07.04.202612
ABC workPRUEBA PEDRO STP - 18.05.202613
ABC workPhase 1 test - 15.09.20261464.0
ABC workTaller - 27.04.202612
ABC workTaller - 29.04.2026719.5
ABC work[TEST] PHASE 1 UX 08-09-2026 - 08.09.2026622.6
ABC work[TRAINING TEST] ABC UX 14-09-202630.4
ABC work[TRAINING TEST] CORE FLOW 14-09-2026 - 14.09.202610.1
ABC workfinal test - 14.09.202612
ABC workTIME RECORDS - JAN-MAY 202632146.0
Named boat/customer workALEXIA - 05.03.2026513.0
Named boat/customer workAlta blue - 13.04.202636
Named boat/customer workAlta blue - 16.06.2026311
Named boat/customer workAquariuos - 02.09.202611
Named boat/customer workAurelius - 03.09.202612
Named boat/customer workBad Romance - 01.09.202621109.0
Named boat/customer workBm comp - 01.05.2026618.0
Named boat/customer workBm comp - 15.06.2026615.0
Named boat/customer workBm comp - 31.03.20261151.5
Named boat/customer workFlight - 15.09.20261252.5
Named boat/customer workKimmora 2 - 21.09.2026624.5
Named boat/customer workKimmuro 2 - 17.09.20261422.0
Named boat/customer workLady k - 13.08.20261371.0
Named boat/customer workLady k - 29.09.202610.5
Named boat/customer workMYSORAH BARNIZ - 21.07.202679383.0
Named boat/customer workMysorah - 10.08.20262464.0
Named boat/customer workPoint Counter Point - 31.07.20262392.5
Named boat/customer workRigPro - 01.09.20261033.5
Named boat/customer workRigPro - 16.09.2026413
Named boat/customer workVelocity - 01.09.2026925.5
Named boat/customer workÁncora - 29.09.202611

Repeated entries to verify

DayWorkerProjectDescriptionHours eachCopiesPotential excess
14Frederico Agusti BergerFlight - 15.09.2026Tbc626
12Francisco Moreno MarinVelocity - 01.09.2026Tbc424
9David Tejada697Taller - 29.04.2026Tbc323
3Adrian ScottBm comp - 01.05.2026Tbc0.520.5

Days above eight hours

WorkerDayEntriesNormalExtraTotal
Adrian Barros Munoz3310010
Arnie Galloway1029.009.0
David Pedrosa Hurtado1548.50.59.0
David Pedrosa Hurtado1637.51.59.0
David Pedrosa Hurtado17327.59.5
David Pedrosa Hurtado183909
David Tejada6972216016
David Tejada6979311011
David Tejada697241909
Francisco Moreno Marin1314.5014.5
Francisco Moreno Marin2316016
Francisco Moreno Marin3316016
Francisco Moreno Marin4213013
Frederico Agusti Berger14212012
J.C. Molina Gonzalez33909
Joaquin Garcia Munoz4314014
Pedro Lopez Lombardo8311.5011.5
Wally Abiodun23212012

Worker daily ledger

WorkerDayABCBoat/customerTotal
Abc14202
Adrian Barros Munoz1088
Adrian Barros Munoz2088
Adrian Barros Munoz301010
Adrian Barros Munoz4066
Adrian Barros Munoz7088
Adrian Barros Munoz8088
Adrian Barros Munoz11066
Adrian Barros Munoz14088
Adrian Barros Munoz15088
Adrian Barros Munoz16088
Adrian Scott11.55.06.5
Adrian Scott312.03.0
Adrian Scott4213
Adrian Scott72.51.54.0
Adrian Scott163.50.54.0
Adrian Scott171.52.54.0
Adrian Scott1811.52.5
Adrian Scott28044
Adrian Scott29145
Adrian Scott302.52.55.0
Arnie Galloway1077
Arnie Galloway207.57.5
Arnie Galloway308.08.0
Arnie Galloway4088
Arnie Galloway7088
Arnie Galloway8088
Arnie Galloway9088
Arnie Galloway1009.09.0
Arnie Galloway11088
Arnie Galloway12066
Arnie Galloway14077
Carlos (Autonomo)14088
Carlos (Autonomo)28011
David Pedrosa Hurtado1358
David Pedrosa Hurtado23.54.58.0
David Pedrosa Hurtado33.52.56.0
David Pedrosa Hurtado4808
David Pedrosa Hurtado7628
David Pedrosa Hurtado95.516.5
David Pedrosa Hurtado10718
David Pedrosa Hurtado11808
David Pedrosa Hurtado143.54.58.0
David Pedrosa Hurtado151.57.59.0
David Pedrosa Hurtado1609.09.0
David Pedrosa Hurtado1718.59.5
David Pedrosa Hurtado18279
David Pedrosa Hurtado22718
David Pedrosa Hurtado28808
David Pedrosa Hurtado2905.05.0
David Pedrosa Hurtado30167
David Tejada6971088
David Tejada697201616
David Tejada6973088
David Tejada6974088
David Tejada697505.55.5
David Tejada6977088
David Tejada6978088
David Tejada69796511
David Tejada6971006.06.0
David Tejada69711268
David Tejada69714088
David Tejada69715088
David Tejada69716088
David Tejada69721088
David Tejada69722088
David Tejada69724099
Donald MacIntyre30718
Francisco Moreno Marin1014.514.5
Francisco Moreno Marin201616
Francisco Moreno Marin301616
Francisco Moreno Marin401313
Francisco Moreno Marin7088
Francisco Moreno Marin8088
Francisco Moreno Marin9088
Francisco Moreno Marin10088
Francisco Moreno Marin11268
Francisco Moreno Marin12088
Francisco Moreno Marin16088
Francisco Moreno Marin17088
Francisco Moreno Marin21088
Francisco Moreno Marin22088
Francisco Moreno Marin23088
Frederico Agusti Berger1088
Frederico Agusti Berger2088
Frederico Agusti Berger3088
Frederico Agusti Berger4088
Frederico Agusti Berger5055
Frederico Agusti Berger7088
Frederico Agusti Berger8088
Frederico Agusti Berger9088
Frederico Agusti Berger10066
Frederico Agusti Berger1108.08.0
Frederico Agusti Berger1401212
Frederico Agusti Berger22808
Frederico Agusti Berger24808
Frederico Agusti Berger28718
J.C. Molina Gonzalez1088
J.C. Molina Gonzalez2033
J.C. Molina Gonzalez3099
J.C. Molina Gonzalez4077
J.C. Molina Gonzalez505.55.5
J.C. Molina Gonzalez7088
J.C. Molina Gonzalez8088
J.C. Molina Gonzalez9358
J.C. Molina Gonzalez10011
J.C. Molina Gonzalez1108.08.0
J.C. Molina Gonzalez12055
J.C. Molina Gonzalez21088
J.C. Molina Gonzalez2208.08.0
J.C. Molina Gonzalez23088
Joaquin Garcia Munoz1077
Joaquin Garcia Munoz2077
Joaquin Garcia Munoz3077
Joaquin Garcia Munoz401414
Joaquin Garcia Munoz7022
Joaquin Garcia Munoz8077
Joaquin Garcia Munoz9077
Joaquin Garcia Munoz11077
Joaquin Garcia Munoz14538
Joaquin Garcia Munoz152.55.58.0
Joaquin Garcia Munoz16808
Jose Crespi Munoz7268
Jose Crespi Munoz8358
Jose Crespi Munoz9235
Jose Crespi Munoz10088
Jose Crespi Munoz1104.04.0
Jose Crespi Munoz14033
Jose Crespi Munoz21088
Jose Crespi Munoz22077
Jose Crespi Munoz23077
Lee Allinson7088
Lee Allinson8088
Lee Allinson9088
Lee Allinson11066
Lee Allinson1405.55.5
Lee Allinson15088
Lee Allinson16055
Linda Perusko Roberts80.100.1
Miguel Angel Morales Vera3808
Miguel Angel Morales Vera46.51.58.0
Miguel Angel Morales Vera76.51.58.0
Miguel Angel Morales Vera8808
Miguel Angel Morales Vera9718
Miguel Angel Morales Vera10628
Miguel Angel Morales Vera114.52.57.0
Miguel Angel Morales Vera14448
Miguel Angel Morales Vera1507.07.0
Miguel Angel Morales Vera16088
Miguel Angel Morales Vera17022
Miguel Angel Morales Vera18066
Miguel Angel Morales Vera2101.51.5
Miguel Angel Morales Vera22033
Miguel Angel Morales Vera23011
Pedro Lopez Lombardo11.567.5
Pedro Lopez Lombardo25.52.58.0
Pedro Lopez Lombardo36.51.58.0
Pedro Lopez Lombardo46.51.58.0
Pedro Lopez Lombardo73.54.58.0
Pedro Lopez Lombardo883.511.5
Pedro Lopez Lombardo96.506.5
Pedro Lopez Lombardo10336
Ruben Sola Fernandez1088
Ruben Sola Fernandez2088
Ruben Sola Fernandez3088
Ruben Sola Fernandez4088
Ruben Sola Fernandez21088
Valentin Garcia Molina14011
Valentin Garcia Molina15268
Valentin Garcia Molina16347
Valentin Garcia Molina21077
Valentin Garcia Molina22088
Wally140.200.2
Wally Abiodun2312012
Wally Abiodun240.300.3

All 320 live source entries

Source order retained within each day. Project links and original descriptions are preserved. No entries removed or corrected.

EntryDayWorkerCategoryProjectNormal/ExtraHoursDescriptionApp path
130Adrian ScottNamed boat/customer workKimmuro 2 - 17.09.2026Normal2.5No description/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
230Donald MacIntyreNamed boat/customer workKimmuro 2 - 17.09.2026Normal1No description/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
330Adrian ScottABC work[TEST] PHASE 1 UX 08-09-2026 - 08.09.2026Normal2.5No description/projects/346b2b03-2d7e-4f53-8319-0819d6927381
430David Pedrosa HurtadoABC workPhase 1 test - 15.09.2026Normal1No description/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
530David Pedrosa HurtadoNamed boat/customer workALEXIA - 05.03.2026Normal6No description/boats/94a28143-4277-4322-bd26-5329355de24e
630Donald MacIntyreABC workPhase 1 test - 15.09.2026Normal7No description/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
729Adrian ScottNamed boat/customer workKimmuro 2 - 17.09.2026Normal2No description/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
829Adrian ScottNamed boat/customer workKimmuro 2 - 17.09.2026Normal1No description/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
929Adrian ScottNamed boat/customer workÁncora - 29.09.2026Normal1No description/projects/15745120-938b-4519-84ee-f3c8e556f77f
1029Adrian ScottABC work[TEST] PHASE 1 UX 08-09-2026 - 08.09.2026Normal1No description/projects/346b2b03-2d7e-4f53-8319-0819d6927381
1129David Pedrosa HurtadoNamed boat/customer workLady k - 29.09.2026Normal0.5No description/projects/bb8cb541-e4a8-4e6b-b744-3fc96f44fd15
1229David Pedrosa HurtadoNamed boat/customer workALEXIA - 05.03.2026Normal4.5No description/boats/94a28143-4277-4322-bd26-5329355de24e
1328Carlos (Autonomo)Named boat/customer workKimmuro 2 - 17.09.2026Normal1No description/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
1428Frederico Agusti BergerNamed boat/customer workKimmuro 2 - 17.09.2026Normal1No description/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
1528Adrian ScottNamed boat/customer workKimmuro 2 - 17.09.2026Normal4No description/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
1628Frederico Agusti BergerABC workPhase 1 test - 15.09.2026Normal7No description/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
1728David Pedrosa HurtadoABC workPhase 1 test - 15.09.2026Normal8No description/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
1824Wally AbiodunABC work[TRAINING TEST] ABC UX 14-09-2026Normal0.1[TRAINING TEST 24-09-2026 T1] Normal time shortcut. Synthetic entry, not labour./projects/f57bd5d7-02af-45f5-a03a-9f520296efc7
1924Wally AbiodunABC work[TRAINING TEST] ABC UX 14-09-2026Extra0.2[TRAINING TEST 24-09-2026 T2] Extra time. Second consecutive shortcut entry, not labour./projects/f57bd5d7-02af-45f5-a03a-9f520296efc7
2024David Tejada697Named boat/customer workKimmora 2 - 21.09.2026Normal9Varnish / barniz - sanding, Kimmura 2. Date 24 September and 9h explicitly confirmed by owner after dictation. Start/end time not established./projects/c2736e01-50d6-41e9-bb06-bc9773498b0b
2124Frederico Agusti BergerABC workPhase 1 test - 15.09.2026Normal8Fur/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
2223Jose Crespi MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal7Varnish / barniz. Dictated timesheet, shift 07:00-15:00; Mysorah allocation 7h, plus separate 1h reunion / meeting./projects/091c8392-19b9-4087-965a-45fd3d135d53
2323Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Paint / pintura - preparation, portion popa (stern). Dictated timesheet, shift 07:00-15:00, 8h; exact preparation wording to confirm./projects/091c8392-19b9-4087-965a-45fd3d135d53
2423J.C. Molina GonzalezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal3Varnish / barniz - first task, 3h allocation. Dictated timesheet, 07:00-15:00; task detail unclear in dictation./projects/091c8392-19b9-4087-965a-45fd3d135d53
2523J.C. Molina GonzalezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal1Varnish / barniz - second task, 1h allocation. Dictated timesheet, 07:00-15:00; task detail unclear in dictation./projects/091c8392-19b9-4087-965a-45fd3d135d53
2623J.C. Molina GonzalezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal4Varnish / barniz - prepare for painting, third task 4h allocation. Dictated timesheet, 07:00-15:00; exact area to confirm./projects/091c8392-19b9-4087-965a-45fd3d135d53
2723Wally AbiodunABC work[TEST] PHASE 1 UX 08-09-2026 - 08.09.2026Normal8Fix/projects/346b2b03-2d7e-4f53-8319-0819d6927381
2823Wally AbiodunABC work[TEST] PHASE 1 UX 08-09-2026 - 08.09.2026Normal4No description/projects/346b2b03-2d7e-4f53-8319-0819d6927381
2923Miguel Angel Morales VeraNamed boat/customer workKimmuro 2 - 17.09.2026Normal1No comments made/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
3022Valentin Garcia MolinaNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal4Paint / pintura - proa preparation; exact task wording unclear in dictation. Shift 07:00-15:00, paint allocation 4h./projects/091c8392-19b9-4087-965a-45fd3d135d53
3122Valentin Garcia MolinaNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal4Varnish / barniz - task wording unclear in dictated timesheet (sounds like rail sanding). Shift 07:00-15:00, varnish allocation 4h; detail to confirm./projects/091c8392-19b9-4087-965a-45fd3d135d53
3222Jose Crespi MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal7Varnish / barniz. Dictated timesheet, shift 07:00-15:00; Mysorah allocation 7h, plus separate 1h non-craft activity./projects/091c8392-19b9-4087-965a-45fd3d135d53
3322Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal7Paint / pintura. Dictated timesheet, shift 07:00-15:00; painting allocation 7h. Sanding / preparation wording requires source confirmation./projects/091c8392-19b9-4087-965a-45fd3d135d53
3422Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal1Varnish / barniz. Dictated timesheet, shift 07:00-15:00; varnish allocation 1h. Exact operation to confirm./projects/091c8392-19b9-4087-965a-45fd3d135d53
3522J.C. Molina GonzalezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal2Varnish / barniz - proa. Dictated timesheet, 07:00-15:00; allocation 1 of 4, 2h. Specific piece not identified./projects/091c8392-19b9-4087-965a-45fd3d135d53
3622J.C. Molina GonzalezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal2.5Varnish / barniz - rail, first 2.5h allocation. Dictated timesheet, 07:00-15:00; rail identity to confirm./projects/091c8392-19b9-4087-965a-45fd3d135d53
3722J.C. Molina GonzalezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal2.5Varnish / barniz - another rail, second 2.5h allocation. Dictated timesheet, 07:00-15:00; rail identity to confirm./projects/091c8392-19b9-4087-965a-45fd3d135d53
3822J.C. Molina GonzalezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal1Varnish / barniz - capa (coat), 1h allocation. Dictated timesheet, 07:00-15:00; full task wording to confirm./projects/091c8392-19b9-4087-965a-45fd3d135d53
3922David Tejada697Named boat/customer workKimmora 2 - 21.09.2026Normal8Varnish / barniz - sanding, Kimmura 2. Dictated timesheet, 8h. Specific piece not identified./projects/c2736e01-50d6-41e9-bb06-bc9773498b0b
4022David Pedrosa HurtadoABC work[TEST] PHASE 1 UX 08-09-2026 - 08.09.2026Normal7Taller/projects/346b2b03-2d7e-4f53-8319-0819d6927381
4122David Pedrosa HurtadoNamed boat/customer workBm comp - 01.05.2026Normal1Big piece/boats/da07b518-131b-4bb7-b871-f8c3f0a9e7af
4222Frederico Agusti BergerABC workPhase 1 test - 15.09.2026Normal8Furgoneta/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
4322Miguel Angel Morales VeraNamed boat/customer workKimmuro 2 - 17.09.2026Normal3No comments/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
4421Valentin Garcia MolinaNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal6Paint / pintura - portion popa (stern). Dictated timesheet, 07:00-15:00, allocation 1 of 3. Exact task wording to confirm./projects/091c8392-19b9-4087-965a-45fd3d135d53
4521Valentin Garcia MolinaNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal1Paint / pintura - patches, non-skid, proa (bow). Dictated timesheet, 07:00-15:00, allocation 2 of 3./projects/091c8392-19b9-4087-965a-45fd3d135d53
4621Jose Crespi MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal4Varnish / barniz. Dictated timesheet, shift 07:00-15:00; Mysorah allocation 4h (other allocations Flight 3h and Kimmura 2 1h). Task detail not legible in dictation./projects/091c8392-19b9-4087-965a-45fd3d135d53
4721Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal6Paint / pintura. Dictated timesheet, shift 07:00-15:00; first Mysorah task 6h. Task wording unclear; retain as allocation 1 of 2 pending source detail./projects/091c8392-19b9-4087-965a-45fd3d135d53
4821Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal2Paint / pintura. Dictated timesheet, shift 07:00-15:00; second Mysorah task 2h. Task wording unclear; retain as allocation 2 of 2 pending source detail./projects/091c8392-19b9-4087-965a-45fd3d135d53
4921J.C. Molina GonzalezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal4Mysorah rail work. Dictated timesheet, 07:00-15:00; allocation 4h (Flight 3h and Kimmura 2 1h recorded separately). Exact operation to confirm./projects/091c8392-19b9-4087-965a-45fd3d135d53
5021Ruben Sola FernandezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal2Paint / pintura - proa (bow), first allocation 2h. Dictated timesheet, shift 07:00-15:00./projects/091c8392-19b9-4087-965a-45fd3d135d53
5121Ruben Sola FernandezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal6Paint / pintura - popa (stern), second allocation 6h. Dictated timesheet, shift 07:00-15:00./projects/091c8392-19b9-4087-965a-45fd3d135d53
5221Jose Crespi MunozNamed boat/customer workFlight - 15.09.2026Normal3Varnish / barniz - Flight of the Dragon (ABC project Flight). Dictated timesheet, 07:00-15:00; Flight allocation 3h./projects/e37198eb-8cfd-4d06-bdb9-a1bed681e3d5
5321J.C. Molina GonzalezNamed boat/customer workFlight - 15.09.2026Normal3Flight of the Dragon (ABC project Flight), 3h. Dictated timesheet, 07:00-15:00; work detail unclear in dictation, pending source confirmation./projects/e37198eb-8cfd-4d06-bdb9-a1bed681e3d5
5421David Tejada697Named boat/customer workFlight - 15.09.2026Normal4Varnish / barniz - Flight of the Dragon (ABC project Flight), 4h. Monday allocation confirmed by owner; other 4h on Kimmura 2./projects/e37198eb-8cfd-4d06-bdb9-a1bed681e3d5
5521Jose Crespi MunozNamed boat/customer workKimmora 2 - 21.09.2026Normal1Varnish / barniz - Kimmura 2 (ABC spelling Kimmora 2). Dictated timesheet, 07:00-15:00; allocation 1h. Specific piece not identified./projects/c2736e01-50d6-41e9-bb06-bc9773498b0b
5621J.C. Molina GonzalezNamed boat/customer workKimmora 2 - 21.09.2026Normal1Kimmura 2 - preparation for painting. Dictated timesheet, 07:00-15:00; corrected final allocation 1h (Mysorah 4h, Flight 3h). Specific piece not identified./projects/c2736e01-50d6-41e9-bb06-bc9773498b0b
5721David Tejada697Named boat/customer workKimmora 2 - 21.09.2026Normal4Varnish / barniz - Kimmura 2. Monday allocation confirmed by owner: 4h here and 4h on Flight. Specific piece not identified./projects/c2736e01-50d6-41e9-bb06-bc9773498b0b
5821Miguel Angel Morales VeraNamed boat/customer workKimmora 2 - 21.09.2026Normal1.5No comment added/projects/c2736e01-50d6-41e9-bb06-bc9773498b0b
5918David Pedrosa HurtadoNamed boat/customer workMysorah - 10.08.2026Normal1TBC/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
6018David Pedrosa HurtadoNamed boat/customer workBm comp - 31.03.2026Normal6TBC/boats/5b9693c7-eced-4340-8b47-1affd6009e5d
6118David Pedrosa HurtadoABC workPhase 1 test - 15.09.2026Normal2TBC/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
6218Adrian ScottNamed boat/customer workMysorah - 10.08.2026Normal0.5Boarding plaque/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
6318Adrian ScottNamed boat/customer workKimmuro 2 - 17.09.2026Normal0.5Prep/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
6418Miguel Angel Morales VeraNamed boat/customer workBm comp - 31.03.2026Normal6Big piece/boats/5b9693c7-eced-4340-8b47-1affd6009e5d
6518Adrian ScottNamed boat/customer workKimmuro 2 - 17.09.2026Normal0.5Tbc/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
6618Adrian ScottABC workTIME RECORDS - JAN-MAY 2026Normal1Afmin/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
6717Adrian ScottNamed boat/customer workMysorah - 10.08.2026Normal0.5Boarding Plaque/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
6817Francisco Moreno MarinNamed boat/customer workRigPro - 01.09.2026Normal8finish/projects/45ffd8a6-1e13-44ff-a95b-1eff5ba10d57
6917David Pedrosa HurtadoNamed boat/customer workRigPro - 01.09.2026Extra7.5TBC/projects/45ffd8a6-1e13-44ff-a95b-1eff5ba10d57
7017David Pedrosa HurtadoNamed boat/customer workMysorah - 10.08.2026Normal1TBC/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
7117David Pedrosa HurtadoABC workPhase 1 test - 15.09.2026Normal1TBC/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
7217Miguel Angel Morales VeraNamed boat/customer workKimmuro 2 - 17.09.2026Normal2Finish/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
7317Adrian ScottNamed boat/customer workKimmuro 2 - 17.09.2026Normal2Degreasing/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
7417Adrian ScottABC workTIME RECORDS - JAN-MAY 2026Normal1.5Admin/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
7516Valentin Garcia MolinaNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal3tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
7616Valentin Garcia MolinaNamed boat/customer workAlta blue - 16.06.2026Normal1tbc/boats/f00e5cdc-7d56-4863-ba81-17e54e164925
7716Valentin Garcia MolinaABC workTaller - 29.04.2026Normal3tbc/boats/603c12e8-bbf7-43bb-b793-21862c2c24f1
7816David Tejada697Named boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
7916Adrian Barros MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
8016Lee AllinsonNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal5No description/projects/091c8392-19b9-4087-965a-45fd3d135d53
8116Adrian ScottABC workPhase 1 test - 15.09.2026Normal1ABC/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
8216Joaquin Garcia MunozABC workPhase 1 test - 15.09.2026Normal8van/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
8316Francisco Moreno MarinNamed boat/customer workBm comp - 31.03.2026Normal5big piece/boats/5b9693c7-eced-4340-8b47-1affd6009e5d
8416Francisco Moreno MarinNamed boat/customer workRigPro - 01.09.2026Normal3finish/projects/45ffd8a6-1e13-44ff-a95b-1eff5ba10d57
8516David Pedrosa HurtadoNamed boat/customer workRigPro - 01.09.2026Extra1.5TBC/projects/45ffd8a6-1e13-44ff-a95b-1eff5ba10d57
8616David Pedrosa HurtadoNamed boat/customer workMysorah - 10.08.2026Normal1TBC/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
8716David Pedrosa HurtadoNamed boat/customer workBm comp - 31.03.2026Normal6.5TBC/boats/5b9693c7-eced-4340-8b47-1affd6009e5d
8816Miguel Angel Morales VeraNamed boat/customer workBm comp - 01.05.2026Normal7Big puece/boats/da07b518-131b-4bb7-b871-f8c3f0a9e7af
8916Miguel Angel Morales VeraNamed boat/customer workRigPro - 01.09.2026Normal1Finish/projects/45ffd8a6-1e13-44ff-a95b-1eff5ba10d57
9016Adrian ScottNamed boat/customer workKimmuro 2 - 17.09.2026Normal0.5Loading/projects/3eb6279a-3e8f-4fdc-9ab1-b20db99b49e2
9116Adrian ScottABC workTIME RECORDS - JAN-MAY 2026Normal2.5Admin/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
9215Valentin Garcia MolinaABC workTaller - 27.04.2026Normal2tbc/boats/3c45bfa2-25a7-4630-a11d-9cb63cd1758b
9315Valentin Garcia MolinaNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal6tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
9415David Tejada697Named boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
9515Adrian Barros MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8TBC/projects/091c8392-19b9-4087-965a-45fd3d135d53
9615Lee AllinsonNamed boat/customer workLady k - 13.08.2026Normal8TBC/projects/dd80e232-6b10-467f-a248-12f073e9b8ed
9715Joaquin Garcia MunozNamed boat/customer workBm comp - 31.03.2026Normal5.5big piece/boats/5b9693c7-eced-4340-8b47-1affd6009e5d
9815Joaquin Garcia MunozABC workPhase 1 test - 15.09.2026Normal2.5van/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
9915David Pedrosa HurtadoNamed boat/customer workRigPro - 01.09.2026Extra0.5No description/projects/45ffd8a6-1e13-44ff-a95b-1eff5ba10d57
10015David Pedrosa HurtadoNamed boat/customer workMysorah - 10.08.2026Normal2.5TBC/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
10115David Pedrosa HurtadoNamed boat/customer workBm comp - 31.03.2026Normal4.5TBC/boats/5b9693c7-eced-4340-8b47-1affd6009e5d
10215David Pedrosa HurtadoABC workPhase 1 test - 15.09.2026Normal1.5TBC/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
10315Miguel Angel Morales VeraNamed boat/customer workBm comp - 15.06.2026Normal5.5Big piece/boats/42f9f20e-e5a1-40bd-8d06-73e2709b5b15
10415Miguel Angel Morales VeraNamed boat/customer workRigPro - 01.09.2026Normal1Finish/projects/45ffd8a6-1e13-44ff-a95b-1eff5ba10d57
10515Miguel Angel Morales VeraNamed boat/customer workMysorah - 10.08.2026Normal0.5High build/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
10614WallyABC work[TRAINING TEST] ABC UX 14-09-2026Normal0.1[TRAINING TEST] Synthetic bench inspection for observational usability walkthrough./projects/f57bd5d7-02af-45f5-a03a-9f520296efc7
10714WallyABC work[TRAINING TEST] CORE FLOW 14-09-2026 - 14.09.2026Normal0.1[TRAINING TEST] Synthetic time entry for controlled flow verification./projects/fae27398-942e-4b43-98c4-919f6eae10b0
10814AbcABC workfinal test - 14.09.2026Normal2No description/projects/1103801a-2154-40f5-aee1-078dfa8ed1bf
10914Adrian Barros MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8TAPAR PINTURA NEGRA Y PREPARAR PARCHES BLANCO/projects/091c8392-19b9-4087-965a-45fd3d135d53
11014Jose Crespi MunozNamed boat/customer workLady k - 13.08.2026Normal1Varnish equipment prep/projects/dd80e232-6b10-467f-a248-12f073e9b8ed
11114Arnie GallowayNamed boat/customer workLady k - 13.08.2026Normal6No issues/projects/dd80e232-6b10-467f-a248-12f073e9b8ed
11214Arnie GallowayNamed boat/customer workLady k - 13.08.2026Normal1Final layer/projects/dd80e232-6b10-467f-a248-12f073e9b8ed
11314Lee AllinsonNamed boat/customer workLady k - 13.08.2026Normal5.5Floor prep/projects/dd80e232-6b10-467f-a248-12f073e9b8ed
11414David Tejada697Named boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Prep work/projects/091c8392-19b9-4087-965a-45fd3d135d53
11514Jose Crespi MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal1Logistics/projects/091c8392-19b9-4087-965a-45fd3d135d53
11614Valentin Garcia MolinaNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal1Paint/projects/091c8392-19b9-4087-965a-45fd3d135d53
11714Jose Crespi MunozNamed boat/customer workFlight - 15.09.2026Normal1Tbc/projects/e37198eb-8cfd-4d06-bdb9-a1bed681e3d5
11814Carlos (Autonomo)Named boat/customer workFlight - 15.09.2026Normal8Tbc/projects/e37198eb-8cfd-4d06-bdb9-a1bed681e3d5
11914Frederico Agusti BergerNamed boat/customer workFlight - 15.09.2026Normal6Tbc/projects/e37198eb-8cfd-4d06-bdb9-a1bed681e3d5
12014Frederico Agusti BergerNamed boat/customer workFlight - 15.09.2026Normal6Tbc/projects/e37198eb-8cfd-4d06-bdb9-a1bed681e3d5
12114David Pedrosa HurtadoNamed boat/customer workBm comp - 15.06.2026Normal4.5Sanding the big piece/boats/42f9f20e-e5a1-40bd-8d06-73e2709b5b15
12214David Pedrosa HurtadoABC workTaller - 29.04.2026Normal3.5Refurbish the varnish accessory box/boats/603c12e8-bbf7-43bb-b793-21862c2c24f1
12314Joaquin Garcia MunozNamed boat/customer workBm comp - 31.03.2026Normal3Primer/boats/5b9693c7-eced-4340-8b47-1affd6009e5d
12414Joaquin Garcia MunozABC workPhase 1 test - 15.09.2026Normal5Refresh/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
12514Miguel Angel Morales VeraNamed boat/customer workBm comp - 31.03.2026Normal4Big piec E/boats/5b9693c7-eced-4340-8b47-1affd6009e5d
12614Miguel Angel Morales VeraABC workPhase 1 test - 15.09.2026Normal4Refresh/projects/f83dbc46-89ed-4db3-9a44-4ab293994b85
12712Francisco Moreno MarinNamed boat/customer workVelocity - 01.09.2026Normal4Tbc/projects/2dcfec0c-5427-4bfa-b60f-1d0194dd5941
12812Francisco Moreno MarinNamed boat/customer workVelocity - 01.09.2026Normal4Tbc/projects/2dcfec0c-5427-4bfa-b60f-1d0194dd5941
12912Arnie GallowayNamed boat/customer workLady k - 13.08.2026Normal6Apply/projects/dd80e232-6b10-467f-a248-12f073e9b8ed
13012J.C. Molina GonzalezNamed boat/customer workFlight - 15.09.2026Normal5Tbc/projects/e37198eb-8cfd-4d06-bdb9-a1bed681e3d5
13111Joaquin Garcia MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal7Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
13211Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal6Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
13311Francisco Moreno MarinABC workTaller - 29.04.2026Normal2Tbc/boats/603c12e8-bbf7-43bb-b793-21862c2c24f1
13411Adrian Barros MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal6Paint/projects/091c8392-19b9-4087-965a-45fd3d135d53
13511Lee AllinsonNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal6Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
13611Arnie GallowayNamed boat/customer workLady k - 13.08.2026Normal8Apply/projects/dd80e232-6b10-467f-a248-12f073e9b8ed
13711David Tejada697Named boat/customer workMYSORAH BARNIZ - 21.07.2026Normal6Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
13811David Tejada697ABC workTaller - 29.04.2026Normal2Thc/boats/603c12e8-bbf7-43bb-b793-21862c2c24f1
13911Frederico Agusti BergerNamed boat/customer workFlight - 15.09.2026Normal5.5Repair/projects/e37198eb-8cfd-4d06-bdb9-a1bed681e3d5
14011Frederico Agusti BergerNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal2.5Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
14111J.C. Molina GonzalezNamed boat/customer workFlight - 15.09.2026Normal5.5Tbc/projects/e37198eb-8cfd-4d06-bdb9-a1bed681e3d5
14211J.C. Molina GonzalezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal2.5Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
14311Jose Crespi MunozNamed boat/customer workFlight - 15.09.2026Normal1.5Tbc/projects/e37198eb-8cfd-4d06-bdb9-a1bed681e3d5
14411Jose Crespi MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal2.5No description/projects/091c8392-19b9-4087-965a-45fd3d135d53
14511Miguel Angel Morales VeraNamed boat/customer workBm comp - 31.03.2026Normal1.5Tbc/boats/5b9693c7-eced-4340-8b47-1affd6009e5d
14611Miguel Angel Morales VeraNamed boat/customer workMysorah - 10.08.2026Normal1Tbc/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
14711Miguel Angel Morales VeraABC workTIME RECORDS - JAN-MAY 2026Normal4.5Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
14811David Pedrosa HurtadoABC workTIME RECORDS - JAN-MAY 2026Normal8Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
14910Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
15010Pedro Lopez LombardoNamed boat/customer workVelocity - 01.09.2026Normal3Paint/projects/2dcfec0c-5427-4bfa-b60f-1d0194dd5941
15110Pedro Lopez LombardoABC workTIME RECORDS - JAN-MAY 2026Normal3Admin/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
15210Arnie GallowayNamed boat/customer workLady k - 13.08.2026Normal5.5Prep/projects/dd80e232-6b10-467f-a248-12f073e9b8ed
15310Arnie GallowayNamed boat/customer workPoint Counter Point - 31.07.2026Normal3.5Tbc/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
15410David Tejada697Named boat/customer workPoint Counter Point - 31.07.2026Normal3.5Tbc/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
15510David Tejada697Named boat/customer workMYSORAH BARNIZ - 21.07.2026Normal2.5Pai t/projects/091c8392-19b9-4087-965a-45fd3d135d53
15610Frederico Agusti BergerNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal6Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
15710J.C. Molina GonzalezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal1Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
15810Jose Crespi MunozNamed boat/customer workFlight - 15.09.2026Normal4Tbc/projects/e37198eb-8cfd-4d06-bdb9-a1bed681e3d5
15910Jose Crespi MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal4Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
16010Miguel Angel Morales VeraNamed boat/customer workMysorah - 10.08.2026Normal2Tbc/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
16110Miguel Angel Morales VeraABC workTIME RECORDS - JAN-MAY 2026Normal6Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
16210David Pedrosa HurtadoABC workTIME RECORDS - JAN-MAY 2026Normal7Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
16310David Pedrosa HurtadoNamed boat/customer workBm comp - 01.05.2026Normal1Tbc/boats/da07b518-131b-4bb7-b871-f8c3f0a9e7af
1649Joaquin Garcia MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal3Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
1659Joaquin Garcia MunozNamed boat/customer workVelocity - 01.09.2026Normal4Tbc/projects/2dcfec0c-5427-4bfa-b60f-1d0194dd5941
1669Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
1679Pedro Lopez LombardoABC workTIME RECORDS - JAN-MAY 2026Normal6.5Admin/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
1689Lee AllinsonNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
1699Arnie GallowayNamed boat/customer workLady k - 13.08.2026Normal8Prep/projects/dd80e232-6b10-467f-a248-12f073e9b8ed
1709David Tejada697ABC workTaller - 29.04.2026Normal3Tbc/boats/603c12e8-bbf7-43bb-b793-21862c2c24f1
1719David Tejada697ABC workTaller - 29.04.2026Normal3Tbc/boats/603c12e8-bbf7-43bb-b793-21862c2c24f1
1729David Tejada697Named boat/customer workAlta blue - 16.06.2026Normal5Tbc/boats/f00e5cdc-7d56-4863-ba81-17e54e164925
1739Frederico Agusti BergerNamed boat/customer workLady k - 13.08.2026Normal8Tbc/projects/dd80e232-6b10-467f-a248-12f073e9b8ed
1749J.C. Molina GonzalezNamed boat/customer workAlta blue - 16.06.2026Normal5Tbc/boats/f00e5cdc-7d56-4863-ba81-17e54e164925
1759J.C. Molina GonzalezABC workTaller - 29.04.2026Normal3Tbc/boats/603c12e8-bbf7-43bb-b793-21862c2c24f1
1769Jose Crespi MunozABC workPRUEBA PEDRO STP - 07.04.2026Normal2TBC/boats/9e65fcf8-037b-435d-b8f4-bc0ab10328a0
1779Jose Crespi MunozNamed boat/customer workVelocity - 01.09.2026Normal3Tbc/projects/2dcfec0c-5427-4bfa-b60f-1d0194dd5941
1789Miguel Angel Morales VeraNamed boat/customer workMysorah - 10.08.2026Normal1Tbc/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
1799Miguel Angel Morales VeraABC workTIME RECORDS - JAN-MAY 2026Normal7Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
1809David Pedrosa HurtadoABC workTIME RECORDS - JAN-MAY 2026Normal5.5Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
1819David Pedrosa HurtadoNamed boat/customer workBm comp - 15.06.2026Normal1Tbc/boats/42f9f20e-e5a1-40bd-8d06-73e2709b5b15
1828Linda Perusko RobertsABC work[TEST] PHASE 1 UX 08-09-2026 - 08.09.2026Normal0.1[DUMMY TEST] Admin entry for Linda — six minutes to validate time capture and linked traceability./projects/346b2b03-2d7e-4f53-8319-0819d6927381
1838Joaquin Garcia MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal7Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
1848Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
1858Pedro Lopez LombardoNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal1.5Rail/projects/091c8392-19b9-4087-965a-45fd3d135d53
1868Pedro Lopez LombardoNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal2Rail and cabina/projects/091c8392-19b9-4087-965a-45fd3d135d53
1878Pedro Lopez LombardoABC workTIME RECORDS - JAN-MAY 2026Normal8Admin/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
1888Adrian Barros MunozNamed boat/customer workRigPro - 01.09.2026Normal3Pulir/projects/45ffd8a6-1e13-44ff-a95b-1eff5ba10d57
1898Adrian Barros MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal5Prep/projects/091c8392-19b9-4087-965a-45fd3d135d53
1908Lee AllinsonNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal3Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
1918Lee AllinsonNamed boat/customer workLady k - 13.08.2026Normal5Sanding/projects/dd80e232-6b10-467f-a248-12f073e9b8ed
1928Arnie GallowayNamed boat/customer workLady k - 13.08.2026Normal8Prep/projects/dd80e232-6b10-467f-a248-12f073e9b8ed
1938David Tejada697Named boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Prep/projects/091c8392-19b9-4087-965a-45fd3d135d53
1948Frederico Agusti BergerNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
1958J.C. Molina GonzalezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
1968Jose Crespi MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal5Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
1978Jose Crespi MunozABC workPRUEBA PEDRO STP - 18.05.2026Normal3Tbc/boats/2d0447d1-0df9-461c-b4fd-4f062986f166
1988Miguel Angel Morales VeraABC workTIME RECORDS - JAN-MAY 2026Normal8Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
1997Joaquin Garcia MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal2Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
2007Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
2017Pedro Lopez LombardoNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal4.5Quitar, lunar, pulir/projects/091c8392-19b9-4087-965a-45fd3d135d53
2027Pedro Lopez LombardoABC workTIME RECORDS - JAN-MAY 2026Normal3.5Admin/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2037Adrian Barros MunozNamed boat/customer workRigPro - 01.09.2026Normal4Lijat/projects/45ffd8a6-1e13-44ff-a95b-1eff5ba10d57
2047Adrian Barros MunozNamed boat/customer workRigPro - 01.09.2026Extra4Extra painting/projects/45ffd8a6-1e13-44ff-a95b-1eff5ba10d57
2057Lee AllinsonNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
2067Arnie GallowayNamed boat/customer workPoint Counter Point - 31.07.2026Normal3Tbc/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2077Arnie GallowayNamed boat/customer workBad Romance - 01.09.2026Normal5Pintar/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2087David Tejada697Named boat/customer workBad Romance - 01.09.2026Normal5Tbc/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2097David Tejada697Named boat/customer workPoint Counter Point - 31.07.2026Normal3Tbc/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2107Frederico Agusti BergerNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
2117J.C. Molina GonzalezNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
2127Jose Crespi MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal6Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
2137Jose Crespi MunozABC workTIME RECORDS - JAN-MAY 2026Normal2Meeting with Duncan/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2147Miguel Angel Morales VeraNamed boat/customer workBm comp - 31.03.2026Normal1.5Tbc/boats/5b9693c7-eced-4340-8b47-1affd6009e5d
2157Miguel Angel Morales VeraABC workTIME RECORDS - JAN-MAY 2026Normal6.5Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2167David Pedrosa HurtadoABC workTIME RECORDS - JAN-MAY 2026Normal6Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2177David Pedrosa HurtadoNamed boat/customer workMysorah - 10.08.2026Normal1Tbc/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
2187David Pedrosa HurtadoNamed boat/customer workVelocity - 01.09.2026Normal1Tbc/projects/2dcfec0c-5427-4bfa-b60f-1d0194dd5941
2197Adrian ScottNamed boat/customer workMysorah - 10.08.2026Normal1Tbc/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
2207Adrian ScottABC workTIME RECORDS - JAN-MAY 2026Normal1.5Van/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2217Adrian ScottABC workTIME RECORDS - JAN-MAY 2026Normal1Other/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2227Adrian ScottNamed boat/customer workVelocity - 01.09.2026Normal0.5Tbc/projects/2dcfec0c-5427-4bfa-b60f-1d0194dd5941
2235J.C. Molina GonzalezNamed boat/customer workPoint Counter Point - 31.07.2026Normal4.5Propspeed/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2245J.C. Molina GonzalezNamed boat/customer workPoint Counter Point - 31.07.2026Normal1Primer/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2255David Tejada697Named boat/customer workPoint Counter Point - 31.07.2026Normal3.5Propspeed/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2265David Tejada697Named boat/customer workPoint Counter Point - 31.07.2026Normal2Paint/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2275Frederico Agusti BergerNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal5Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
2284J.C. Molina GonzalezNamed boat/customer workPoint Counter Point - 31.07.2026Normal7Apply/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2294David Tejada697Named boat/customer workPoint Counter Point - 31.07.2026Normal5Apply/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2304David Tejada697Named boat/customer workPoint Counter Point - 31.07.2026Normal3Paint/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2314Ruben Sola FernandezNamed boat/customer workBad Romance - 01.09.2026Normal3Cabins/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2324Ruben Sola FernandezNamed boat/customer workMysorah - 10.08.2026Normal5Prep/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
2334Joaquin Garcia MunozNamed boat/customer workBad Romance - 01.09.2026Normal7Prep/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2344Joaquin Garcia MunozNamed boat/customer workMysorah - 10.08.2026Normal4No description/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
2354Joaquin Garcia MunozNamed boat/customer workBad Romance - 01.09.2026Normal3Prep/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2364Francisco Moreno MarinNamed boat/customer workMysorah - 10.08.2026Normal8Parches/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
2374Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal5Wash and mask/projects/091c8392-19b9-4087-965a-45fd3d135d53
2384Arnie GallowayNamed boat/customer workPoint Counter Point - 31.07.2026Normal3Apply/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2394Arnie GallowayNamed boat/customer workMysorah - 10.08.2026Normal5Apply/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
2404Frederico Agusti BergerNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
2414Pedro Lopez LombardoNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal1.5Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
2424Pedro Lopez LombardoABC workTIME RECORDS - JAN-MAY 2026Normal6.5Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2434Adrian Barros MunozNamed boat/customer workRigPro - 16.09.2026Normal4Tbc/projects/ae9a4e97-a20c-4deb-a6b8-cfc98774e024
2444Adrian Barros MunozNamed boat/customer workVelocity - 01.09.2026Normal2Tbc/projects/2dcfec0c-5427-4bfa-b60f-1d0194dd5941
2454David Pedrosa HurtadoABC workTIME RECORDS - JAN-MAY 2026Normal8Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2464Miguel Angel Morales VeraABC workTIME RECORDS - JAN-MAY 2026Normal6.5Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2474Miguel Angel Morales VeraNamed boat/customer workBm comp - 15.06.2026Normal1.5Tbc/boats/42f9f20e-e5a1-40bd-8d06-73e2709b5b15
2484Adrian ScottNamed boat/customer workMysorah - 10.08.2026Normal1Tbc/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
2494Adrian ScottABC workTIME RECORDS - JAN-MAY 2026Normal2Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2503J.C. Molina GonzalezNamed boat/customer workAlta blue - 13.04.2026Normal2N/boats/c4237802-ead2-4fd4-acb2-1c251ef5abac
2513J.C. Molina GonzalezNamed boat/customer workAlta blue - 13.04.2026Normal1Capa/boats/c4237802-ead2-4fd4-acb2-1c251ef5abac
2523J.C. Molina GonzalezNamed boat/customer workPoint Counter Point - 31.07.2026Normal6Apply antifoul/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2533David Tejada697Named boat/customer workPoint Counter Point - 31.07.2026Normal3High build/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2543David Tejada697Named boat/customer workPoint Counter Point - 31.07.2026Extra5Fix/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2553Ruben Sola FernandezNamed boat/customer workMysorah - 10.08.2026Normal8Paint/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
2563Joaquin Garcia MunozNamed boat/customer workBad Romance - 01.09.2026Normal7Prep/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2573Francisco Moreno MarinNamed boat/customer workBad Romance - 01.09.2026Normal8No description/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2583Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal2Sanding and demask/projects/091c8392-19b9-4087-965a-45fd3d135d53
2593Francisco Moreno MarinNamed boat/customer workPoint Counter Point - 31.07.2026Normal6Apply/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2603Arnie GallowayNamed boat/customer workPoint Counter Point - 31.07.2026Normal5.5Apply/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2613Arnie GallowayNamed boat/customer workMysorah - 10.08.2026Normal2.5Apply/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
2623Frederico Agusti BergerNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal8Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
2633Pedro Lopez LombardoNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal1.5TBC/projects/091c8392-19b9-4087-965a-45fd3d135d53
2643Pedro Lopez LombardoABC workTIME RECORDS - JAN-MAY 2026Normal6.5Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2653Adrian Barros MunozNamed boat/customer workRigPro - 16.09.2026Normal4Tbc/projects/ae9a4e97-a20c-4deb-a6b8-cfc98774e024
2663Adrian Barros MunozNamed boat/customer workVelocity - 01.09.2026Normal4Tbc/projects/2dcfec0c-5427-4bfa-b60f-1d0194dd5941
2673Adrian Barros MunozNamed boat/customer workAurelius - 03.09.2026Normal2Tbc/projects/8d3924a8-4488-4c9f-b482-22c5eb659361
2683David Pedrosa HurtadoNamed boat/customer workALEXIA - 05.03.2026Normal1Tbc/boats/94a28143-4277-4322-bd26-5329355de24e
2693David Pedrosa HurtadoNamed boat/customer workBad Romance - 01.09.2026Normal1.5Tbc/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2703David Pedrosa HurtadoABC workTIME RECORDS - JAN-MAY 2026Normal3.5Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2713Miguel Angel Morales VeraABC workTIME RECORDS - JAN-MAY 2026Normal8Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2723Adrian ScottNamed boat/customer workBm comp - 01.05.2026Normal0.5Tbc/boats/da07b518-131b-4bb7-b871-f8c3f0a9e7af
2733Adrian ScottNamed boat/customer workALEXIA - 05.03.2026Normal0.5Tbc/boats/94a28143-4277-4322-bd26-5329355de24e
2743Adrian ScottNamed boat/customer workBad Romance - 01.09.2026Normal0.5Tbc/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2753Adrian ScottNamed boat/customer workBm comp - 01.05.2026Normal0.5Tbc/boats/da07b518-131b-4bb7-b871-f8c3f0a9e7af
2763Adrian ScottABC workTIME RECORDS - JAN-MAY 2026Normal1Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2772J.C. Molina GonzalezNamed boat/customer workAlta blue - 13.04.2026Extra3Extra/boats/c4237802-ead2-4fd4-acb2-1c251ef5abac
2782David Tejada697Named boat/customer workBad Romance - 01.09.2026Normal8Prepare all the parches/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2792David Tejada697Named boat/customer workPoint Counter Point - 31.07.2026Normal8Paint/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2802Ruben Sola FernandezNamed boat/customer workBad Romance - 01.09.2026Normal8Prepare/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2812Joaquin Garcia MunozNamed boat/customer workBad Romance - 01.09.2026Normal7Prep/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2822Francisco Moreno MarinNamed boat/customer workBad Romance - 01.09.2026Normal8Paint/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2832Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal3Topcoat/projects/091c8392-19b9-4087-965a-45fd3d135d53
2842Francisco Moreno MarinNamed boat/customer workPoint Counter Point - 31.07.2026Normal5Apply/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2852Arnie GallowayNamed boat/customer workPoint Counter Point - 31.07.2026Normal3Paint/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2862Arnie GallowayNamed boat/customer workMysorah - 10.08.2026Normal4.5Apply/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
2872Frederico Agusti BergerNamed boat/customer workBad Romance - 01.09.2026Normal8Tbc/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2882Adrian Barros MunozNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal3Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
2892Pedro Lopez LombardoNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal2.5TBC/projects/091c8392-19b9-4087-965a-45fd3d135d53
2902Pedro Lopez LombardoABC workTIME RECORDS - JAN-MAY 2026Normal5.5Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2912Adrian Barros MunozNamed boat/customer workRigPro - 16.09.2026Normal3Tbc/projects/ae9a4e97-a20c-4deb-a6b8-cfc98774e024
2922Adrian Barros MunozNamed boat/customer workRigPro - 16.09.2026Normal2Tbc/projects/ae9a4e97-a20c-4deb-a6b8-cfc98774e024
2932David Pedrosa HurtadoNamed boat/customer workAquariuos - 02.09.2026Normal1Tbc/projects/8fdb83be-2621-47eb-b30d-f9ee290c3157
2942David Pedrosa HurtadoNamed boat/customer workBad Romance - 01.09.2026Normal1.5Tbc/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
2952David Pedrosa HurtadoNamed boat/customer workBm comp - 15.06.2026Normal1Tbc/boats/42f9f20e-e5a1-40bd-8d06-73e2709b5b15
2962David Pedrosa HurtadoNamed boat/customer workMysorah - 10.08.2026Normal1Tbc/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
2972David Pedrosa HurtadoABC workTIME RECORDS - JAN-MAY 2026Normal3.5Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
2981J.C. Molina GonzalezNamed boat/customer workPoint Counter Point - 31.07.2026Extra5Lunar primocom/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
2991J.C. Molina GonzalezNamed boat/customer workPoint Counter Point - 31.07.2026Normal3Apply antifoul/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
3001David Tejada697Named boat/customer workBad Romance - 01.09.2026Normal7Prepare with 545/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
3011David Tejada697Named boat/customer workPoint Counter Point - 31.07.2026Normal1Apply antifoul/projects/3382cf44-a5e8-4d7b-8ba7-54f83b78fea6
3021Joaquin Garcia MunozNamed boat/customer workBad Romance - 01.09.2026Normal7Prep/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
3031Francisco Moreno MarinNamed boat/customer workMysorah - 10.08.2026Normal4Parches/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
3041Francisco Moreno MarinNamed boat/customer workBad Romance - 01.09.2026Normal4Prep/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
3051Francisco Moreno MarinNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal6.5Sand and washdown/projects/091c8392-19b9-4087-965a-45fd3d135d53
3061Arnie GallowayNamed boat/customer workMysorah - 10.08.2026Normal6Apply/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
3071Arnie GallowayNamed boat/customer workLady k - 13.08.2026Normal1Prep/projects/dd80e232-6b10-467f-a248-12f073e9b8ed
3081Frederico Agusti BergerNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal3Tbc/projects/091c8392-19b9-4087-965a-45fd3d135d53
3091Frederico Agusti BergerNamed boat/customer workBad Romance - 01.09.2026Normal5Tbc/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
3101Pedro Lopez LombardoNamed boat/customer workMYSORAH BARNIZ - 21.07.2026Normal6Thc/projects/091c8392-19b9-4087-965a-45fd3d135d53
3111Pedro Lopez LombardoABC workTIME RECORDS - JAN-MAY 2026Normal1.5TBC/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
3121David Pedrosa HurtadoNamed boat/customer workALEXIA - 05.03.2026Normal1Tbc/boats/94a28143-4277-4322-bd26-5329355de24e
3131David Pedrosa HurtadoNamed boat/customer workBad Romance - 01.09.2026Normal4Tbc/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
3141David Pedrosa HurtadoABC workTIME RECORDS - JAN-MAY 2026Normal3Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
3151Adrian ScottNamed boat/customer workBad Romance - 01.09.2026Normal1.5Tbc/projects/76b0bff5-593e-43b3-9b30-f18c76b01969
3161Adrian ScottNamed boat/customer workBm comp - 15.06.2026Normal1.5Tbc/boats/42f9f20e-e5a1-40bd-8d06-73e2709b5b15
3171Adrian ScottNamed boat/customer workMysorah - 10.08.2026Normal2Tbc/projects/fe8ac9c9-fb17-43d4-98b0-c2edfe6da1e2
3181Adrian ScottABC workTIME RECORDS - JAN-MAY 2026Normal1.5Tbc/projects/199be0d0-8257-4a20-af5f-d139bcd8e5f8
3191Adrian Barros MunozNamed boat/customer workBm comp - 01.05.2026Normal8Big door/boats/da07b518-131b-4bb7-b871-f8c3f0a9e7af
3201Ruben Sola FernandezNamed boat/customer workBm comp - 31.03.2026Normal8No description/boats/5b9693c7-eced-4340-8b47-1affd6009e5d

Source: https://abcdashboard-production.up.railway.app/time-tracking. Review date: 2026-10-02. Attendance, leave, payroll, rates, billability, invoice approval and physical work location were not established by this view.